Illustrative image – not actual.The department is ready to approach the Maharashtra Electricity Regulatory Commission (MERC) for approval after which it will float tenders.
Once the plants are commissioned, some of the existing old thermal plants will be retired in line with the Centre’s resolve to phase out power plants older than 25 years and replace them with supercritical ones.
While each unit of a supercritical thermal plant has a generation capacity of 660 MW, the two units coming up in Umred have a higher generation capacity.
The new units will not add to the state’s existing generation capacity, as it will replace the existing one.
The Maharashtra State Power Generation Company has already decommissioned two units of 210 MW each at the Chandrapur power plant, one 210 MW unit at Parli plant and one 200 MW unit at Koradi power plant.