Illustrative image – not actual.
The government of Maharashtra has given its approval for Pimpri Chinchwad Municipal Corporation's (PCMC) ambitious water supply scheme under Atal Mission for Rejuvenation and Urban Transformation (Amrut) projects.
The estimated cost of the 24x7 water supply project is Rs 123 crore.
The civic body will implement the first phase under Jawaharlal Nehru National Urban Renewal Mission of having round the clock water supply covering 40 percent of the area or 54,000 water connections.
The remaining 60 percent of the project or 74,000 water connections will be covered in the second phase.
The state government has also given approval to start the tendering process. The implementing agency will have to complete the project in two years.
The main water pipeline will be 5.1 km, while high density poly ethyl pipes of 119.855 km, and ductile iron pipes in the distribution system of 50.260 km will be laid. Two elevated storage reservoirs, each of two million ltr capacity, will also be constructed.
Bids will be invited for the electrical works component of the project at an estimated cost of about Rs 102 crore.
PCMC will bear the responsibility in case of additional project cost.