Illustrative image – not actual.BSES has sought the Maharashtra state government's clearance for its proposed 550 MW thermal power project at Nandgaonpeth at Amravathi in Maharashtra. The estimated cost of the project is Rs.2,278 crore. BSES plans to bring in these funds from its internal accruals.
According to BSES, the cost of
power per mega watt would be Rs.4.55 crore, while the per unit cost would be
Rs.2.25 during the first year of operation.
BSES has proposed that the power
generated from the plant be supplied to the state through an allocation of
distribution lines so as to make the project economically viable. This proposal
would be discussed during a meeting convened by the state chief minister, Mr,
Vilasrao Deshmukh on 9 January 2001.
Meanwhile, Tata Power and
Maharashtra State Electricity Board have expressed reservation about the
project as the same could adversely affect their finances due to a possible
fall in the sale of power generated by them.