Illustrative image – not actual.The Maharashtra state government plans to seek Rs.15,000 crore from World Bank for funding infrastructure projects in the state. A meeting between the two parties would be held on 7 November 2000.
The state government plans to use the funds to the following projects:
· Expansion of the 69 MW Parli thermal power station in Marathwada to 250 MW. The project, which is estimated cost Rs.1,054 crore, has received clearance from the Central Electricity Authority.
· The Rs.2,948 crore transmission and distribution schemes formulated by the Maharashtra State Electricity Board. These schemes are expected to be completed within three years and are expected to add 2,000 ckt km and 4,000 MVA. Under this scheme the government would undertake the following projects:
Ø Setting up new substations at Patalganga, Butibori, Solapur, Jejuri and Akola at an estimated cost of Rs.348 crore.
Ø Construction of a 80 EHV substation with voltage ranging from 100 kv to 220 kv. The estimated cost of this project would be Rs.900 crore.
Ø Upgrading various links and substations at an estimated cost of Rs.300 crore.
Ø Improving systems, urban renovation and rural electrification with a total cost of Rs.1,400 crore.
· The Mumbai Urban Transport Project (MUTP) phase II, which is estimated to cost Rs.6,000 crore. The MUTP is a railway renovation and modernisation project being implemented by the Mumbai Rail Vikas Corporation.
· Urban infrastructure projects such as rehabilitation of slum dwellers and other redevelopment programmes.
· Rural development and drinking water projects.