Illustrative image – not actual.On 26 December 2007, Maharashtra government extended the time for eight independent power producers to commission their projects by September 2011. The eight power producers include
| Company | Capacity (MW) | Location |
| Tata Power | 1,500 | Trombay, |
| Reliance Energy | 4,000 | Shahpur, Alibaug |
| Jindal Thermal Power | 1,000 | Jaigad, Ratnagiri |
| Central India Power Co | 2,000 | Badrawati, Chandrapur |
| Ispat Energy | 1,000 | Pen, Raigad |
| Essar Power | 1,500 | Ville Bhagad, Raigad |
| Spectrum Technology | 500 | Alibaug, Raigad |
| GMR Energy | 1,000 | Vidharbha Region |
Of the above eight companies, only the first five private players have responded to government, whereas the other three has not adhered to these conditions.