Illustrative image – not actual.The Maharashtra Cabinet on 4 February 2021 approved implementation of the Chief Minister Water Conservation Programme, costing Rs 1,340.75 crore.
Under the programme, water sources will be repaired, which will enhance the state’s irrigation capacity.
The period of the programme is from April 2020 to March 2023.
Out of the completed sources, 7,916 need to be repaired, and water storage and irrigation capacity need to be restored. If these are revived, water will be available at full capacity.
Under the programme, various ponds and lakes with irrigation capacity up to 600 hectares would be repaired. Also, repair work of canals due to breakage of its lining will also be undertaken.
Under the programme, water sources will be repaired, which will enhance the state’s irrigation capacity.
The period of the programme is from April 2020 to March 2023.
Out of the completed sources, 7,916 need to be repaired, and water storage and irrigation capacity need to be restored. If these are revived, water will be available at full capacity.
Under the programme, various ponds and lakes with irrigation capacity up to 600 hectares would be repaired. Also, repair work of canals due to breakage of its lining will also be undertaken.