Illustrative image – not actual.The Maharashtra Cabinet, on 1 November 2006, gave its in-principle approval to Line 2 of the Mumbai metro rail project. The MMRDA board had cleared the Rs.6,192 crore project on 28 September 2006. With the state cabinet approval now in place, MMRDA can proceed with the tendering process.
MMRDA plans to develop the 31.87 km fully elevated line from Charkop to Mankhurd (via Bandra) on BOOT basis with a concession period of 35 years. MMRDA will hold 26 per cent in the special purpose vehicle with the private sector holding the remainder.
Line 2, connecting the eastern and western suburbs of Mumbai, is expected to be ready by 2011. It will have 27 stations en route at ground clearances of 5-12m.
Transport studies have forecast that by 2011, 12.75 lakh people will use the line daily. By 2021, this number will have risen to 18.77 lakh and for 2031, the forecast is 22.16 lakh people.
Viability gap funding: In an independent development, the Public-Private Partnership Appraisal Committee, on its meeting on 1 November 2006 deferred the decision on the viability gap funding of Rs.650 crore for Mumbai Metro Rail projects, as the new Secretary for the Ministry of Urban Development, Mr. M Ramachandran, took charge on 1 November 2006, itself.
The finance ministry is unwilling to consider the Mumbai Metro Rail project under the PPP-AC, as it had been bid out before the committee was formed. The finance ministry was keen that the project be taken up under the Jawaharlal Nehru Urban Renewal Mission. A decision in this regard was to be taken by PPP-AC on 1 November 2006.
Also See:
Mumbai metro rail project: Line 2 approved (29-Sep-06)
Mumbai metro project: MMRDA proposes changes in Line 2 (09-Aug-06)