Illustrative image – not actual.On 10 January 2007, the Maharashtra cabinet gave its approval for the generation capacity addition of 2,000 MW by Maharashtra Power Generation Co (Mahagenco).
The projects will come at Parli (250 MW), Paras (250 MW), Khaparkheda (500 MW) and Bhusawal (1,000 MW) with a total investment of Rs.8,000 crore. All projects represent expansion (adding of units) to existing power stations.
The contract for boilers, turbines and generators will be placed to Bharat Heavy Electricals for these projects through negotiation route. Output from the Mahanadi coalfields allotted by the centre to Maharashtra and Gujarat will help partially meet coal requirement for these upcoming projects. Besides, the company will also seek coal linkage from the coal ministry.
Also See:
Mahagenco to use "negotiated route" for Parli, Paras projects (08-Aug-06)
(ProjectsToday adds: This news item is merely a formal announcement made by the Maharashtra Cabinet on 10 January 2007. The four power projects are already in the pre-project work phase.)