Mahanadi project Unit-II to be commissioned next yearIllustrative image – not actual.

KSK Energy Ventures is planning to commission Unit-II of the 600 MW Mahanadi thermal power plant in Chhattisgarh by next year.

 

The boiler light up for Unit-II of the 6 x 600 MW project and commissioning of the turbine generator are likely to be completed within 45-60 days. Other related works are also expected to be implemented by that time to enable the company to commission the unit.

 

The company commissioned Unit-I of the project in May 2013, which is now functional with all associated ancillary infrastructure.

 

Besides, KSK Mahanadi has entered into a power purchase pact (PPA) for 500 MW with Tamil Nadu Generation and Distribution Corp. This has been done through competitive bidding.

 

The company is investing $3.6 billion (around Rs 22,450 crore) in the coal-fired plant. It will supply power to Gujarat, Chhattisgarh, Goa, Andhra Pradesh and other states.

 

It has long-term coal supply arrangements with Gujarat Mineral Development Corp and Goa Industrial Development Corp. Besides, it has a tapering linkage with Coal India for immediate needs.

 