Illustrative image – not actual.Maharashtra State Power Generation Co (Mahagenco) has reportedly decided to opt for the "negotiated route" for awarding the boiler, turbine and generator (BTG) package for the upcoming Parli and Paras expansion projects. Reports suggest that the BTG contract would be placed on Bharat Heavy Electricals for both the projects. The development follows a state cabinet decision that has allowed the negotiated route in favour of tendering.
Mahagenco is in the midst of adding 2,000 MW by expanding four of its existing units -- Paras, Parli, Kharperkheda and Bhusawal -- at a total cost of Rs.8,609 crore. Mahagenco will finance the projects to the extent of 20 per cent (equity component of the 80:20 debt-equity ratio), while the remaining 80 per cent would come through borrowings.
The following is a quick summary of the future course of action:
Paras (1x250 MW) & Parli (1x250 MW)
- BTG package to be awarded to BHEL on a negotiated basis.
- Global tenders will be invited for the civil package
Khaparkheda (1x500 MW)
- BTG package targeted for award by September 2006 (bids already invited)
Bhusawal (2x500 MW)
- International bids for BTG package will be invited by 30 August 2006; selection by October 2006
Also See: