Illustrative image – not actual.The projects have been bagged by Azure Power and Shapoorji Pallonji. The auction was completed in April 2018, and the letter of award (LoA) will be issued soon. Power purchase agreements (PPAs) will be signed in June 2018.
Azure Power has won the bid to develop 200 MW of solar PV projects for supplying power to AG feeders across the state of Maharashtra. The company will enter a 25 year power purchase agreement (PPA) with MAHAGENCO at a tariff of Rs 3.07 per kWh. The project is expected to be commissioned in 2019.
Shapoorji Pallonji has won bid to develop 50 MW of solar PV projects for supplying to AG feeders across the state. The company will enter 25 year PPA with MAHAGENCO at a tariff of Rs 3.26 per kWh.
MAHAGENCO will provide free land to developers for these projects.
Another 100 MW will be awarded soon, out of which 50 MW may go to Azure and 50 MW may go to Shapoorji Pallonji.