Madhya Pradesh seeks to revoke ban on dam projectIllustrative image – not actual.

The Madhya Pradesh Government has requested the Union Government to cancel its order to suspend the work on the Maheshwar hydro electric project.

In mid-April 2010, the MoEF ordered the suspension of work on the 400 MW Maheshwar project on Narmada river, citing non-compliance of environmental norms.

The Ministry found that no agriculture land was identified for rehabilitation of affected people. Out of the 22 villages that faced submergence threat, rehabilitation was completed in only one village, it noted. Also, two wildlife sanctuaries had not been developed as directed by it.

The state government has written a letter to the Union Government mentioning a loss of 7.2 lakh units of power per day starting in November 2010 and denial of 360 million litres per day water for the urban areas of Dewas and Indore districts, in case the suspension order is not revoked.

Related Links:
Project profile 