Machilipatnam Port Project: Foundation stone laidIllustrative image – not actual.

On 23 April 2008, Andhra Pradesh Chief Minister, Mr.YS Rajasekhara Reddy, is scheduled laid the foundation stone for Rs.1,590 crore Machilipatnam deep water port project in Krishna district.

The state government has awarded the project to a consortium comprising Maytas Infra (MIL), Nagarjuna Construction Co, SREI Infrastructure, and Sarat Chatterjee & Company, on build, own, operate and transfer (BOOT) basis.

Financial closure for the project is likely to be achieved within a period of 12 months and the first phase of the port is scheduled for completion within 24 months from the date of commencement of work. The first phase envisages an investment of Rs.1,590 crore, and three berths will be built to handle 15 million tpa of cargo a year. The combined length of north and south breakwaters will be 6,900 metres.