Illustrative image – not actual.Tenders invited for drainage and breakwater works at the proposed Machilipatnam Port project, in Krishna district of Andhra Pradesh, are expected to be finalised by November.
The project is being executed by the consortium of Maytas Infrastructure, Nagarjuna Construction Co, SREI Infrastructure Finance and Sarat Chatterjee & Co., in which, NCC holds 25 per cent stake, Maytas 26 per cent, and SREI Infrastructure 38 per cent. The balance 11 per cent will be held by a privately-owned firm (owned by Satyam chairman, Mr.B Ramalinga Raju).
The project has been conceived over 3,000 acres of land and at a cost of Rs.1,600 crore. It will be implemented on BOT basis. Consulting Engineering Services, Delhi, has been appointed as project consultant. Financial closure and environmental clearance are likely to be in place by December 2008.
Work on the project is likely to commence by January 2009 and is scheduled for completion within 24 months.