L&T’s plea to increase tariff for Punjab plant rejected Illustrative image – not actual.

The Appellate Tribunal for Electricity (Aptel) has discarded a proposal of L&T Power Development to increase tariff for its coal-based power plant in Punjab.


The company stated that its proposed cost escalation of Rs 51 crore for the 1,400 MW power project, due to changes in the detailed engineering of the project, had necessitated the increase.


L&T had submitted that the change was required as the project promoter, Punjab State Power Corporation, had given incorrect information in the bidding documents about the seismic sensitivity of the site. While the site fell in seismic zone IV, the documents erroneously mentioned it as zone II.


According to the tribunal, the developer had issued a disclaimer on the accuracy of data provided in the documents, and so the bidder should have made its own inquiries.


The 2 x 700 MW power plant is being undertaken by Nabha Power, owned by L&T Power Development, at an investment of Rs 9,600 crore.


Besides, the Appellate Tribunal for Electricity has accorded approval for the other proposal of L&T, seeking sanction of Rs 178 crore cost escalation caused by change in the work scope of railway siding of the project stipulated by the Railways.

 