Larsen & Toubro (L&T) that had bagged the contracts to redevelop Naigaum and Worli BDD chawls in Mumbai, Maharashtra, has decided to withdraw from the Naigaum project.
The government failed to fulfill its commitment of moving out the tenants and handing over the land to the company for redevelopment. Hence, the company has sought to withdraw from the project.
The Naigaum project was estimated to cost Rs 2,400 crore and to be completed within seven years in three phases. With no movement on the ground and escalating project cost, the construction firm thought it best to pull out.
L&T had constructed a sample flat at the site so residents will be encouraged to allow the redevelopment. In Phase-I, 10 chawls comprising 800 tenements were to be redeveloped.
The Naigaum plot is spread over 13.4 acre and the gross construction area was estimated at 6.7 lakh sq mtr.
MHADA had tentatively planned to build four sale buildings with 60 floors each at Naigaum. The authority had also proposed a 20 storey commercial structure, besides 20 buildings with 19 to 23 floors to house the existing tenants of the Naigaum chawls.
There are four clusters of BDD chawls in Mumbai -- Naigaum, N M Joshi Marg, Worli and Sewri. The Naigaum and Worli projects were bagged by L&T while the Tata Group had bagged the N M Joshi project.