Illustrative image – not actual.L&T Metro Rail (Hyderabad) is likely to finalise vendors for rolling stock and signalling equipment by June 2012, for the metro rail project in Hyderabad.
Along with vendors for rolling stock, the company will finalise operations and maintenance contractors for the project. At least four major vendors, including Canadian supplier of rolling stock, Bombardier, a Spanish firm, China CSR Corporation and the BEML-Rotem consortium are in fray for the Rs 1,800-crore deal. Also, L&T intends to execute Transit-Oriented Development along the corridor, and ensure connectivity through multiple modes of transport. Initially, six million sq ft of mixed use space will be taken up.
The Rs 16,375-crore project has an equity component of Rs 3,439 crore, viability gap funding of Rs 1,458 crore from the Central Government and a term loan component of Rs 11,478 crore. So far, L&T has invested Rs 500 crore as equity contribution.