Illustrative image – not actual.Larsen & Toubro has started the widening and strengthening work on the two-lane carriageway on NH-5, which forms part of the Golden Quadrilateral. The company had bagged this project from National Highway Authority of India under the international competitive bidding process.
The Minsiter of State for Road Transport and
Highways, Major General (Retd) B C Khanduri, laid the foundation stone for this
project at Madhavaram near Chennai.
The scope of the project work involves construction
of 13 bridges of different spans, six underpasses, one overpass and 78
culverts. The work will start from Madhavaram and end at Tada in Andhra
Pradesh, covering a distance of 41.8 km.
The project is estimated to cost Rs.233 crore, though
the domestically funded contract value is Rs.185 crore.
The project work is expected to be completed within 31
months, after which congestion on the national highway leading to Vijaywada and
Kolkata will be reduced.