L&T flags off three heavy LC-Max reactors for HPCL's Visakh RefineryIllustrative image – not actual.
Larsen & Toubro (L&T) flagged off three LC-Max reactors weighing 2,313 tonne each to the Hindustan Petroleum Corporation’s (HPCL) Visakhapatnam Refinery in Andhra Pradesh.

The three reactors will be deployed at the country's first residue upgrade facility (RUF) by HPCL's Visakh Refinery Modernisation Project five months ahead of schedule.

These reactors will convert the heaviest crudes to high-quality BS-VI diesel, as well as increase feedstock and improve product flexibility.

The reactors, designed and built in collaboration with Engineers India, will sail in single piece directly to Visakhapatnam from L&T's fully integrated, modern coastal manufacturing facility at Hazira in Gujarat.

The project was initially scheduled to be completed in 20 months but due to the pandemic, an additional 10 months were given. However, the company could complete the project within 25 months.

HPCL has Rs 25,000 crore worth of orders with L&T as part of its Rs 1.1 lakh crore capital expenditure (capex) plan ending 2024.

The Rs 26,264 crore Visakh Refinery Modernisation Project will increase the capacity from 8.33 million tonne to 15 million tonne and is shceduled for comminssioning in mid-2022, from the originally planned mid-2020. The original project cost was fixed at Rs 20,928 crore.