Larsen & Toubro (L&T)) has been declared the lowest bidder (L1) by Uttar Pradesh Metro Rail Corporation (UPMRCL) to carry out the civil construction work of package AGCC-07 of Agra Metro Line-2. This comparise various key components including a complete elevated viaduct with 14 stations along Line 2, and a 530-mtrs. viaduct leading to the Kalindi Vihar Depot.
With a bid value of Rs 1,466.49 crore, L&T will also be responsible for 2.61 km viaduct extension covering north of the Sadar Bazar Metro station to Line-1’s PAC Depot. The AGCC07 contract also integrates the work initially assigned to the AGCC-06 package, which was scrapped.
In December 2023, UPMRCL floated the tender to construct Package AGCC-07 with an estimated cost of Rs 1,529.29 crore and a timeline of 24 months.