Illustrative image – not actual.L&T has bagged orders worth a total Rs 1,749 crore.
The company in consortium with Italy based Paul Wurth, has been awarded a Rs 1,627 crore EPC contract to build the 2.8 million tpa Blast Furnace for SAIL-Bhilai Steel Plant. L&T's share in the contract is Rs 1,010 crore.
L&T in consortium with Outotec, GmbH of Germany, won an EPC contract of Rs 670 crore to build a 3.7 million tpa Sinter Plant for SAIL - Bhilai Steel Plant. Its share in the contract is Rs 538.29 crore.
The company also won an additional order of Rs 201crore from BALCO for capacity expansion of its Aluminium Smelter at Korba in Chhattisgarh. This order is in addition to the large package being executed by L&T for the BALCO expansion project. This involves setting up of 340 kAmps Potline and Carbon Area including Supply, Fabrication, Construction, Erection and Project Monitoring services.