Illustrative image – not actual.Larsen & Toubro has bagged substation orders worth Rs.853 crore collectively. This includes contract from
Abu Dhabi Water & Electricity Authority for design, supply, installation and commissioning of the two 132/22 kV substations at Saadiyat Island in Abu Dhabi. Mott MacDonald is the consultant to the project.
Each Substation consists of 132 kV gas insulated switchgear 22 kV gas insulated switchgear 63/80MVA 132/22 kV tansformers, substation control & monitoring system, protection & telecommunication system, DC system & auxiliaries and substations. The contract also encompasses design and construction of the substation buildings together with the associated utilities. The contract valued at Rs.366 crore will be completed within 18 months.
The company has secured yet another order for turnkey construction at 400/220 kV extra high voltage substations valued at Rs.200 crore from the Power Grid Corporation of India. One of these major substation is to be located at Gurgaon (Near Delhi) will be 400/220 kV gas insulated substations. The other air insulation substations will be located at Bhinmal and Kankroli in Rajasthan and Zerda in Gujarat.
The scope of work includes supply, erection testing & commissioning of 315 MVA transformers, 400 kV reactors, substation automation & protection system and total civil & air-conditioning works.
ECC's Water and Utilities group has also bagged three orders valued at Rs.287 crore.
Tamil Nadu Water Supply & Sewerage Board awarded an order for Rs.195 crore for implementation of comprehensive water supply schemes in Ramanathapuram, Sivagangai and Pudhukottai districts in Tamil Nadu. The water project in Tamil Nadu includes supply, install, testing and commissioning of mild steel and pre-stressed concrete pipelines. Scope also includes construction of storage reservoirs and electro-mechanical works. This contract is to be completed in 18 months.
Delhi Jal Board (DJB) awarded an EPC order of value Rs.92.50 crore for design, providing, laying, jointing, testing and commissioning of 22 km of 1200 mm diameter mild steel raw water transmission main from Wazirabad raw water pump house to proposed water treatment plant at Okhla. DJB shall be able to pump 22 MGD raw water to the water treatment plant at Okhla and shall be distributed to Outer Delhi and South Delhi. This contract is to be completed in 20 months. (project details)