Illustrative image – not actual.L&T Energy CarbonLite Solutions has secured a limited notice to proceed (LNTP) from NTPC for the main plant package of the 2x800 MW Lara Stage-III thermal power project in Chhattisgarh.
The formal Notice to Proceed will be issued after completion of the LNTP period and receipt of environmental clearance for the project. The contract involves the construction of two advanced 800 MW ultra-supercritical generating units, strengthening India's baseload power generation capacity. Under the EPC scope, L&T will undertake the design, engineering, manufacturing, supply, erection, testing, and commissioning of major plant components, including boilers, steam turbines, generators, electrostatic precipitators (ESPs), air-cooled condensers (ACC), and associated auxiliaries. The company will also execute mechanical, electrical, control and instrumentation, and civil works required for the project.
Once commissioned, the Lara Stage-III project will contribute 1,600 MW of reliable electricity generation capacity to India's power grid.