Illustrative image – not actual.Malana Power Co. Ltd, part of the LNJ Bhilwara Group has invited industrial groups in Northern or Western India to participate in its new hydro-electric plant in Himachal Pradesh.
The plant would be developed jointly,
as a captive power plant. Interested parties would have to invest around Rs.30
to Rs.50 crore in the project, and should have an energy demand of at least 100
million kwh per annum.
The
project details are:
Project
|
Allain Duhangan Hydel Project |
|
Capacity |
192 MW (2 x 96 MW) |
|
Location |
Kullu District of Himachal Pradesh (4 km southeast of Manali town) |
|
Generation |
700 million kwh per year |
|
Approvals |
1.
40 year concession agreement from Govt of HP 2.
Environmental Clearance obtained |
|
Construction |
Can commence in 3-6 months |
For
more details, contact:
A
B Giri
Executive
Director (Power)
Bhilwara
Towers
A-12,
Sector 1
Noida
201 301
Uttar
Pradesh
e-mail:
[email protected]
The LNJ Bhilwara Group has recently
commissioned its 86 MW Malana Hydel Project,
in a record time of 2.5 years. Earlier, it had commissioned its 15 MW Tawa
Hydel Project in less than two years. Besides, the Group also operates 45.5 MW
of co-generation and liquid fuel based captive power plants.