Illustrative image – not actual.The 126 MW Larji hydropower project being developed by Himachal Pradesh State Electricity Board in Mandi district of the state, is scheduled to be commissioned by middle of 2005.
The first unit of 42 MW would start trial runs in March 2005, while the other two units of like capacity would be commissioned in the two months thereafter.
The excavation work of the 35 metre diameter surge shaft has been completed and concreting and lining will be finished by March 2005.
The construction of powerhouse was also in the final stages.