Land acquisition hurdles between Byappanahalli and KR Puram are delaying the Byappanahalli-Whitefield corridor of the Bengaluru Metro Rail Project. Metro work on the Seetharampalya (Visvesvaraya Industrial Area)-Whitefield section is progressing fast.
In 2017, BMRCL had awarded the contract for the 15 km elevated Byappanahalli-Whitefield corridor to ITD Cementation India and it was supposed to be ready by 2020.
The deadline was extended to August 2021 and has now been revised to June 2022. The corridor under Metro’s Phase-2 is an extension of the existing Purple Line (Mysuru Road-Byappanahalli) and will have 13 stations.
Around 95 percent of civil work between Seetharampalya and Whitefield has been completed till October 2020. For the Byappanahalli-Seetharampalya section, the figure is 80 percent.
ITD Cementation completed all segmental spans (2,125 segments) of viaduct between Seetharampalya and Whitefield. The section will have stations like Kundalahalli, Nallurhalli (Vydehi Hospital), Sadaramangala (Satya Sai Hospital), Pattandur Agrahara (ITPB), Kadugodi, Channasandra (Ujjval Vidyalaya) and Whitefield.
In October 2019, the Bangalore Metro Rail Corporation (BMRCL) had awarded the contract for construction of depot structures, site development work, internal roads and drainage to Vascon Engineers at a cost of around Rs 160 crore. The work is supposed to be completed in two years.
The eight km Byappanahalli-Seetharampalya section will take at least two more years. Stations on the route include Benniganahalli (Jyothipura), KR Puram, Saraswati Nagar (Mahadevapura), Gurudacharpalya and Hoodi Junction (Doddanekundi).
Since Benniganahalli station may get delayed, BMRCL is planning to operate trains between Whitefield and Byappanahalli via KR Puram without the station. It will be constructed later.
Three Metro lines — Byappanahalli-Whitefield, ORR-Kempegowda International Airport and depot entry line — will pass through Tin Factory junction. The section between KR Puram station and Tin Factory will have a six-lane road on the southern side and five-lane one on the northern side. A two-lane additional flyover from Tin Factory to Kasturinagar is also part of the road infrastructure.