Illustrative image – not actual.Land allotment for the construction of a depot is delaying the construction of Mumbai Metro One's Versova-Andheri-Ghatkopar Metro Rail Project (Line I of Phase I) .
The state government, in particular the MMRDA, was expected to allot land for a depot at DN Nagar in Andheri and for casting yards at Wadala for the project. MMOPL has completed most of the background work for the project and possession of the land is the only pending issue for delay in the construction work of the project.
So far, the MMOPL has carried out several surveys for the first corridor and tenders for civil work and rolling stock have been submitted by the short-listed bidders, tenders for the remaining contracts are expected by October 2007.