Illustrative image – not actual.Work on Surya Food Agro’s biscuits processing unit in Khurda district of Odisha is set to begin in November 2018, as confirmed with Projects Today. The process to acquire land is underway from July 2018.
The food processing project being set up at Khordha Food Park will have a capacity of 60,000 tpa. The State Level Single Window Clearance Authority (SLSWCA) had sanctioned the Rs 292.5 crore project in July 2017.
During the period of development, the project is expected to generate around 650 jobs. Contractor and consultant for the project will be chosen from in-house team.