Land acquisition of 15.37 ha of land for providing rail connectivity to Vallarapadam International Container Transhipment Terminal (ICTT) has not begun.

Although the final location survey is taken up, only 30 km of the proposed route is surveyed. As much as 131 hectares of land is required, against which land acquisition proposals have been given by Railways in respect of 56.22 ha.

Rail Vikas Nigam Limited (RVNL) under the Union Ministry of Railways has been entrusted with the work, for which tenders have been floated. RVNL is likely to finalise the tenders by September 2008. The proposed railway link, 7 km in length, will have a 3.5 km bridge. The Rs.215 crore project is scheduled for completion by March 2009.