The land acquisition process for the expansion of Chakeri airport, Kanpur, has started.
Chakeri airport is an international standard airport. There has not been any flight service from the airport -- which is under the control of the Indian Air Force -- for the last 3-4 years.
The district administration has already started the process of acquiring 20 ha of land in Machaiya village, adjacent to the airport. Of the 20 ha, 17 belong to farmers and the remaining three ha to the Gram Samaj.
Of the 17 farmers whose land is to be acquired, the process of acquisition has been completed with respect to 12. The entire process of acquisition will be completed and compensation paid in the next 20-25 days. The compensation for the Gram Samaj land will be remitted to the account of the state government.
Once the acquisition is completed, the land will be handed over to the Airport Authority of India (AAI) so that they can start the work. The airport is expected to be operational again by the end of 2017.