Land acquisition for Chennai Metro’s Phase-II project nearing completion Illustrative image – not actual.

The construction of the Chennai Metro Rail (CMRL) Phase-II project has picked up momentum, with about 92 percent of the land having been acquired by the authorities.

The Phase-II of the project mandates development to be carried out on 115.6 hectares of land, while the transport utility has taken possession of 106.3 hectares. The process is underway to acquire the remaining land and is expected to be completed soon.

Earlier, only 112.72 hectares of land was required but now additional land parcels are needed along the Old Mahabalipuram Road (OMR) and it has gone up to 115.6 hectares of land. The acquisition of additional land was necessitated as the CMRL decided to make changes in the plan to avoid walkways getting affected.

The project will now cover 116 km of the city with 118 stations planned in a way so as to ensure that most areas of the city have access to the mass rapid transit system (MRTS).

The stations will be built in three corridors, which include Madhavaram to SIPCOT (45.4 km - Corridor III, Light House to Poonamallee (26.1 km - Corridor IV) and Madhavaram to Sholinganallur (44.6 km – Corridor V).

The first stretch to get ready would be between Poonamallee and Porur, which is a part of corridor IV, and pockets of land needed for station construction along the stretch has already been acquired.