Land acquisition for bullet train project completed Illustrative image – not actual.

The land acquisition for the bullet train connecting Mumbai to Ahmedabad under National High Speed Rail Corridor has been completed. As per National High Speed Rail Corporation (NHSRSL), construction activity has begun in the elevated part of the bullet train corridor in Maharashtra, for the section which comprises a total 135 km from Shilphata near Mumbai till Zaroli village on Maharashtra-Gujarat boundary.

The elevated part of the project comprising six mountain tunnels, 36 crossings including 11 steel bridges and river bridges on Ulhas, Vaitarna and Jagani rivers is also amongst the most challenging part. The longest river bridge of 2.32 km of the project is in this section on Vaitarna river, and this particullar section also includes three bullet train stations in Thane, Virar and Boisar, which come under Mumbai Metropolitan Region (MMR).

Currently, cleaning and grubbing works for 78 km is underway, and geotechnical investigation is under progress at the site with 50 percent completion rate. Open foundation has been constructed at 19 locations, and is ongoing at 42 locations.

The bullet train is expected to cut by half the time taken to travel the distance of 508 km between Mumbai and Ahmedabad. The 352 km section through Gujarat will fully open in 2027. A section of 50 kms from Surat to Bilimora is expected to open in August 2026.

← All latest storiesBack to top →