Land acquisition has been completed for construction of Phase-1B extension of Kochi Metro Rail Line from SN junction to Tripunithura.
As part of the process the Revenue Authorities handed over the documents related to the land acquisition to Kochi Metro Rail (KMRL) for further proceedings.
A total of 2.3238 ha land has been acquired for the Metro project. The distribution of compensation to 80 land owners also has been completed.
KMRL is planning to extend the Metro rail to SN Junction from Petta station as Phase-1(A) extension and from SN Junction to Tripunithura, railway station as Phase-1 (B) extension.
While the former goes through the road from Petta to SN Junction, the latter will be implemented as an elevated corridor.
The works of Phase-1(A) extension have already been completed. The nodal agency is planning to commission the track by June 2022, after service trial next week. The first phase work of Phase-1(B) extension to Tripunithura, is also progressing at the land that was already acquired in Phase-1 acquisition.
Metro works on 50 percent of land acquired in the first phase has been completed. Around 68 percent of piling works for the stations on the stretch and 30 percent of the piling works for the track laying have been completed. Phase 1-B extension is planned to be commissioned by 2023.