Land acquisition commences for Thane-Borivali tunnel projectIllustrative image – not actual.
The land acquisition process has started for Thane-Borivali tunnel project in Maharashtra which will reduce travel time between the two suburbs from one hour to 15 minutes. 
 
The detailed project report (DPR) is ready and the tunnel is expected to be operational in 2028. The Maharashtra Urban Development Minister EknathShinde noted the authority will be using tunnel boring technology to avoid disrupting the park’s biodiversity. 
 
The minister said the project did not require environmental clearances. This twin tunnel will connect Thane and Borivali in approximately 15 minutes, providing commuters with significant relief. 
 
The project to be implemented by the Mumbai Metropolitan Region Development Authority (MMRDA) is estimated to cost Rs 11,235.43 crore and will ease pressure on Ghodbunder Road.  
 
The 11.8 km long dedicated tunnel, including 10.25 km stretch beneath Sanjay Gandhi National Park, will run from Tikuji-Ni-Wadi in Thane to the Western Express Highway in Borivali. 
 
The twin tunnels of three-plus-three lanes each will connect the Western Express Highway (NH-3) and Ghodbunder Road (SH-42).  The project will require the acquisition of 16.54 ha private land and 40.46 ha land within the Sanjay Gandhi National Park. 
 
Scheduled to begin in March 2022, the project is expected to take five-and-a-half years to complete. It will have cross tunnels at every 300 mtr, and the design will allow vehicles to travel at top speed of 80 km per hour. 
 
The project is also estimated to reduce consumption of fuel by 10.5 lakh tonne. The initiative will contribute to 36 percent reduction in carbon dioxide emissions. The tunnels will have a drainage system, smoke detectors and jet fans.