The land acquisition process has commenced for Rs 1,500 crore Ambala Ring Road project. The Union government has marked 41 villages in Ambala and nine in Mohali, Punjab.
The acquisition process will take up to six months. The Central and state governments had approved the project earlier in June 2021.
Of these, 41 are in Ambala and nine in Dera Bassi, Mohali, while 40 km road will cover 177.75 ha.
As per an official document issued by the Ministry of Road Transport and Highways (MoRTH), the proposed highway will cover 10 villages in Ambala, 29 in Cantonment, two in Saha and nine in Dera Bassi, Mohali.
The 40 km long ring road project will be spread across 177.75 ha of land and connect five national highways and work as a bypass to ease traffic congestion in the twin city.
The vehicles coming from Hisar, Chandigarh, Amritsar, bound for Uttar Pradesh, Delhi, Uttarakhand or Himachal, will have an option to bypass Ambala.
Similarly, traffic coming from Delhi or Yamunanagar going towards Punjab or Chandigarh need not enter urban areas of Cantt or City.
The Ring Road will start from NH-152 (Ambala-Chandigarh Highway) and link with NH-72 (Ambala-Roorkee Highway, now NH-344).
It will lead to NH-444A (Ambala-Saha Highway) that will link with NH-44 (Delhi-Amritsar highway or GT Road) and then, GT Road will finally connect with NH-65 (Ambala-Hisar Highway).
Moreover, a digital display board will be installed at toll plazas showing the project cost, the amount recovered through toll collection and the period of levy of toll for the project cost.