Adani Cementation is planning to set up a new cement grinding unit in Karnataka. The total capacity of the unit will be two million tpa, based on Vertical Roller Mills (VRM)/ Roller Press technology.

The greenfield unit will be located within the existing Udupi Power Corporation's (UPCL) premises at the Karnataka Industrial Areas Development Board (KIADB). The plant will be implemented in two phases.

As confirmed with Projects Today, the promoter has already acquired land and financial closure is in process. Once the environment clearance is received, the company intends to commence the project work by November 2018. The project is expected to be completed in two years.

The project is spread over 35 acre of land and will be funded by 35 percent through equity and the balance through bank loans.