Lanco power project approaches financial closureIllustrative image – not actual.

The 300 MW coal-based power project of Lanco Amarkantak Power Pvt Ltd (LAMPPL) is expected to achieve financial closure soon.

Power Finance Corporation, the lead financial arranger is reported to have formalized the debt component with a consortium of banks and financial institutions. Financial closure is expected within the next three months. The Rs.1,275 crore project is being financed through a debt-equity ratio of 70:30. PFC and its consortium partners would be financing the project to the tune of Rs.892 crore. Of the remaining Rs.383 crore of equity, the Lanco group would be bringing in 77 per cent, with the remaining being held by its local partner, the KVK group.

The Pathadi power project will be expanded to 600 MW in Phase II. Agreements with Power Trading Corporation for long term energy sale and with South Eastern Coalfields, for supply of coal, have already been entered into.

The project is headed for completion by June 2007.