Illustrative image – not actual.Lanco Infratech has filed a claim under the ‘advanced loss of profit’ (ALOP) policy for delay in its power project in Uttar Pradesh.
The company has filed a claim of around Rs 200 crore under the ALOP policy. The claim was made after fire broke out at the company’s 1,200 MW Anpara power project in Uttar Pradesh in April 2011, which damaged a part of the boiler. The 600 MW Unit I which became operational in early November 2011, was originally scheduled to be commissioned in May 2011. Hence, the company has made claims for the delay. The Unit II of the power project has also been commissioned in November 2011. Lanco has signed the PPAs with distribution companies of Uttar Pradesh State Electricity Board.