Illustrative image – not actual.Lalitha Cement is setting up a 2,300 tpd cement unit with supported by a 15 MW coal-based power plant at Raghunathpalayam in Nalgonda district of Andhra Pradesh.
Financial closure is likely by end-December 2006 and the PPA will be signed by early January 2007. The machinery for the power plant would be sourced from abroad, wherein orders have already been placed for supply of equipment for the cement plant. The civil contractor would also be finalized with the next 15 days.
The Rs.150 crore project would be funded through 33 per cent internal accruals and balance through loans.
Currently, site-leveling work is underway. Commercial production is likely to commence by April 2008.
Related links:
Project
profile