Lakhwar-Vyasi hydel project faces delaysIllustrative image – not actual.

The 420 MW Lakhwar-Vyasi multi-purpose hydel project on the river Yamuna near Dakpathar, 50 km from Dehradun, is clouded by uncertainties due to cost overruns and inordinate delays.

The project evinced during 1970s was estimated to cost around Rs 141 crore. Now it has gone up to Rs 4,000 crore with the Uttarakhand government awarding the project to Uttarakhand Jal Vidyut Nigam Ltd (UJVNL) in 2008.

However, the real worry for UJVNL is the project's liabilities as various works were carried out in the past by different players like NHPC and Jaypee Group. NHPC has already sought a claim of Rs 75 crore from UJVNL for preparing the DPR and other works of the project.

On completion, the project is likely to produce 852 million units of power besides irrigating 40,000 ha through east Yamuna canal.  