Lake Turkana wind power project to connect national grid by SeptemberIllustrative image – not actual.
The Lake Turkana wind power project in Loiyangalani, Marsabit county in Kenya, is expected to be connected to the national grid by September 2018.

This will be done following the handing over to a Chinese contractor to set up the remaining section of high voltage wires for evacuation of the green energy.

The wind farm with a capacity of 310 MW was supposed to connect the first 50 MW into the grid in October 2016 and the remaining capacity by July 2017.

The power line linking the 310 MW wind power plant to the national grid is 70 percent complete.

The power project for which USD 56 million was allocated is expected to be completed by the end of August 2018 and once completed, a clean and affordable power will be distributed to consumers.