Illustrative image – not actual.Lafarge India's second clinker line at its existing Sonadih cement plant at Balodabazar in Raipur district of Chhattisgarh has gone on-stream on 6 January 2010.
The new clinkerisation unit is expected to have a capacity of 1.6 million tpa clinker and is to more than double the production of the existing Sonadih plant. Currently, the plant produces 1.4 million tpa of the cement making raw material.
The additional produce is likely to cater to the requirement of Sonadih and Jojobera (Jharkhand) plants and contribute to scale up their overall cement production capacity in the long run.