Lack of funds stops sewerage project midwayIllustrative image – not actual.
Punjab deputy chief minister, Sukhbir Singh Badal, had announced that the Rs 28 crore sewerage project at Baghapurana town in the district would be completed in eight months, but the work has been stopped for the last five years due to shortage of funds.

 

The foundation stone was laid in March 2011 and was handed over to the civic body after completion on November 30, 2011.

 

A sum of Rs 20 crore was spent on the project till December 2012. After that, the government did not release the instalment of Rs six crore and construction work was abandoned midway.

 

The project included sewerage work, water supply, reconstruction of roads after putting the underground pipeline and other expenses.

 