Illustrative image – not actual.A consortium comprising Larsen &
Toubro among four other companies has bagged a Rs.1,650 crore contract for the
construction of an underground corridor for Delhi Metro Rail Corporation
(DMRC).
The members of the joint venture
executing the contract are:
|
Company |
Country |
|
Larsen & Toubro |
India |
|
Dyckerhoff & Widdmann AG |
Germany |
|
Samsung Corporation |
Korea |
|
Shimizu Corporation |
Japan |
|
IRCON International |
India |
The corridor would connect the ISBT
station to Central Secretariat. The total duration of the contract is 59 months
and the project would be largely funded by the Japan Bank for International
Co-operation.
The ISBT-Central Secretariat corridor
is a 7 km route out of the total distance of 39 km of the Mass Rapid Transport System
(MRTS) being implemented by DMRC.
The total cost of MRTS is estimated at
Rs.5,211 crore, which is 7.2 per cent higher than the Rs.4,860 crore envisaged earlier.
The entire project was expected to be completed by March 2005, as per estimates
of the Ministry of Planning made in February 2001.