Illustrative image – not actual.Unit-II of the Kudankulam Nuclear Power Plant (KKNPP), which is coming up at Kudankulam, Tirunelveli district in Tamil Nadu, is expected to be operational by September 2014.
Around 95 per cent of the work for Unit-II of the plant has been completed and is expected to generate electricity from September 2014.
The power project has been undertaken by Nuclear Power Corporation of India (NPCIL) and is estimated to cost Rs 17,270 crore.
Unit-I of KKNPP has already started producing electricity and is now synchronised with the southern grid.
Electricity generated from Unit-I of the power project is 440 MW and all the power goes to Tamil Nadu. Soon, production of Unit-II will be increased to 750 MW and after receiving the necessary permissions from the Atomic Energy Regulatory Board (AERB), the plant will start generating 1,000 MW of electricity by February 2014.
Related Link:
Project profile