Illustrative image – not actual.Nuclear Power Corporation of India's (NPCIL) is likely to commence commercial generation of the first unit of Kudankulam Nuclear Power Project (KNPP), by November 2013.
The 1,000 MW unit has achieved 99.76 per cent physical progress in September 2013. In August 2013, the Atomic Energy Regulatory Board (AERB), gave its nod to KNPP to raise the reactor power levels to 50 per cent and to synchronise the unit with the power grid. The NPCIL earlier said it would connect the first unit to the grid by end August, generating 400 MW power. But that did not happen due to two condenser valve problems.
Meanwhile, the second unit at KNPP is expected to start commercial operations in June next year. The unit has achieved progress of 96 per cent as of September 2013.