Illustrative image – not actual.
CERC, by its order dated 10 November, has permitted NPCIL to feed infirm power into the southern gird from its Unit-I, till 22 January 2015, in response to a petition by the nuclear power plant operator.
Infirm power is the one that is generated by a power unit that has not begun commercial operations.
NPCIL had made the application to CERC seeking its permission to feed infirm power till 22 January 2015, or till the unit achieves commercial operation, whichever is earlier.
CERC had earlier permitted NPCIL to feed infirm power from Unit-I into the grid till 10 October, 2014. However, the unit stopped operations on September 26 as its turbine blades and diaphragm were damaged.
According to NPCIL, the turbine problem is expected to be resolved by 22 December 2014, and one month's time is needed for eventualities.
NPCIL, in collaboration with Russia, is setting up the Kudankulam power plant, in Tirunelveli district of Tamil Nadu. The project will be implemented in two units of 1,000 MW each, with a total investment of Rs 17,270 crore.
First criticality was achieved for the 1,000 MW Unit-I in July 2013, following which the unit was connected to the southern grid in November 2013, and reached full capacity generation in June 2014.
More Project Info:
Kudankulam Atomic Power Project