KSL & Industries has announced that it would take up a Rs.600 crore programme over the next two years to expand its textiles manufacturing capacity.

Objective: The plan aims to add 1.5 lakh spindles for manufacturing of cotton yarn. There will be a corresponding increase in knitting, fabric processing and garment manufacturing facilities. Currently, the company has a spinning capacity of 65,000 spindles (translating to around 10,000 tpa of yarn), 19,000 tpa of knitting capacity with 200 machines and 1,000 tpa of textile processing capacity. The project also involves setting up of a coal-based captive power plant (capacity unknonwn.)

Location: Taluka Kalameshwar, dist. Nagpur, Maharashra.

Project Financing: Around Rs.400 crore would be raised as debt through the Textile Upgradation Fund Scheme (TUFS) of the Union government. The remaining would come through equity (proposed IPO) and internal accruals.

Current Status: Land has been acquired and project work has already begun.

Completion: The project is targeted for completion by March 2006.