Illustrative image – not actual.KSK Energy Ventures is expected to augment the size of the Wardha Chhattisgarh project from the initial proposed 1,800 MW to 3,600 MW. The change in the capacity of the project requires the clearance of the Chhattisgarh government.
The project which entails an investment of Rs 16,200 crore is to have a debt-equity ratio of 75:25.
The company has entered into a fuel supply agreement with Goa Industrial Development Corporation which has been allotted Gare Pelma sector-III coal block in the state. This block is estimated to host about 215 million tonne of coal reserves. The detailed project feasibility studies were conducted by RITES.