Hyderabad-based KSK Energy Ventures will be setting up a 540 MW coal-based power project at Warora in Chandrapur district of Maharashtra with an investment of Rs.2,400 crore.

The company has floated a special purpose vehicle (SPV) - Wardha Power Company Pvt Ltd (WPCPL) - to execute the project. The project to be spread over 94 ha of land will be implemented in two phases (270 MW each) and will have four units of 135 MW each. The Chinese company, SEDC is supplying the equipment and all the clearances have been achieved for the project.

KSK Energy has achieved financial closure for Phase I (270 MW) and has sourced funds worth Rs.555 crore from Rural Electrification Corporation, HUDCO (Rs.233 crore) and Indian Overseas Bank (Rs.100 crore) on loan basis. The 270 MW (two units of 135 MW) project has been tied up with Tarapore-based Viraj Profiles, which is also chipping in with equity along with KSK Energy (total equity of Rs.600 crore). A 25 year power purchase agreement at a uniform price negotiated already has been signed.

The company has entered into an arrangement with Gujarat Mineral Development Corporation (GMDC), which has been allocated a coal block in Chhattisgarh, for the supply of fuel for the project. While GMDC will do the mining, KSK Energy will retain the right to invest up to 26 per cent of the equity of the power project

Work on Phase I was scheduled for completion by May 2009, while Phase II will be synchronised by the end-2009.